# ELSIB installs new turbogenerator at Pavlodar CHP-3

A new turbogenerator produced by ELSIB was installed at Pavlodar CHP-3 on September 8, 2018, increasing the station's capacity by 15 MW. The generator replaced an older unit and has a capacity of 125 MW.

- Type: Expansion
- Announced: 2018-09-08
- Where: Pavlodar, Kazakhstan, Kazakhstan
- Starts operating: 8 Sep 2018
- Status: completed
- Capacity: 125 MW
- Products: turbogenerator
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [ELSIB](https://endata.com/companies/34349.md) (supplier)
- [Pavlodar CHP-3](https://endata.com/companies/34350.md) (customer)

## Sources

- [proektgaz.do.am](https://proektgaz.do.am/news/na_pavlodarskoj_tehc_3_ustanovili_turbogenerator_proizvodstva_ehlsib/2018-09-17-941), 2018-09-17: "Мощность новой установки – 125 МВт"

---