Nava Nakorn Electricity Generating Co. (NNEG) has started construction of a 60-MW expansion phase at its power plant in the Nava Nakorn industrial zone, Thailand. The 3.105-billion-baht project is scheduled for commercial operation in 2020, increasing total capacity to 185 MW.

- Type: Expansion
- Announced: 2018-09-10
- Where: Nava Nakorn industrial zone, Thailand
- Value: $94.0M (3.10B THB)
- Starts operating: 2020
- Status: under construction
- Capacity: 60 MW electricity, 10 ton/hour steam
- Products: electricity, steam
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Nava Nakorn Electricity Generating Co.](https://endata.com/companies/34220.md)
- [IHI](https://endata.com/companies/6049.md) (supplier)
- [Ratchaburi Electricity Generating Holding PCL](https://endata.com/companies/34221.md) (investor)
- [Nava Nakorn Public Company Limited](https://endata.com/companies/34222.md) (investor)
- [Global Power Synergy Public Company Limited](https://endata.com/companies/34223.md) (investor)
- [Jurong Engineering Limited](https://endata.com/companies/34224.md) (supplier)
- [Thai Jurong Engineering Limited](https://endata.com/companies/34225.md) (supplier)

## Sources

- [ratch.co.th](https://www.ratch.co.th/en/updates/company-news/39/nneg-concluded-epc-contract-for-construction-of-60-mw-expansion-phase-to-serve-customers-power-demand-in-nava-nakorn-industrial-zone-after-the-64-billion-baht-debentures-offering-achieved), 2018-09-10: "The expansion phase was consistently progressing towards the construction stage."

---