# Reliance Infrastructure wins Rs 3,647 Cr EPC contract for Uppur thermal power project

Reliance Infrastructure (RInfra) won an EPC contract worth Rs 3,647 crore from TANGEDCO for the balance of plant package and allied civil works for the 2 x 800 MW supercritical coal-based Uppur Thermal Power Project in Ramanathapuram District, Tamil Nadu. The project is to be commissioned in 36 months.

- Type: Contract
- Announced: 2018-02-22
- Where: Ramanathapuram District, Tamil Nadu, India
- Value: $560.0M (36.5B INR)
- Status: announced
- Capacity: 2 x 800 MW
- Products: thermal power plant balance of plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Reliance Infrastructure](https://endata.com/companies/23956.md)
- [Tangedco](https://endata.com/companies/2588.md) (customer)
- [Tamil Nadu Generation and Distribution Corporation Ltd](https://endata.com/companies/28855.md) (customer)

## Sources

- [moneycontrol.com](https://www.moneycontrol.com/news/business/rinfra-bags-rs-3647-cr-contract-for-thermal-power-project-in-tamil-nadu-2513695.html), 2018-02-22: "RInfra has won a prestigious engineering, procurement and construction (EPC) contract for Rs 3,647 crore from TANGEDCO for balance of plant (BoP) package and allied civil works for 2 x 800 MW supercritical coal-based Uppur Thermal Power Project at Ramanathapuram District in Tamil Nadu."
- [miningconnection.com](https://miningconnection.com/coal_prep/news/article/reliance_infrastructure_secures_56_million_contract_for_uppur_thermal_power), 2018-02-27: "Reliance Infrastructure has won a contract worth INR3,647crore ($562m) to provide balance of plant (BoP) package and associated civil works for the 1.6GW Uppur thermal power project in the Indian state of Tamil Nadu."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.