# Dewa awards Siemens and Elsewedy $300M contract for H station expansion

Dubai Electricity and Water Authority awarded a $300 million contract to a consortium of Siemens and Elsewedy for the fourth phase of the H station at Al Aweer, adding 815 MW capacity. Three gas turbines will be operational from February to April 2020.

- Type: Contract
- Announced: 2018-02-07
- Where: Al Aweer, Dubai, United Arab Emirates
- Value: $300.0M
- Status: announced
- Capacity: 815 MW
- Products: gas turbines, electricity generators
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Siemens](https://endata.com/companies/301.md) (supplier)
- [Dubai Electricity and Water Authority](https://endata.com/companies/5624.md) (customer)
- [Elsewedy](https://endata.com/companies/29925.md) (supplier)

## Sources

- [thenationalnews.com](https://www.thenationalnews.com/business/energy/dewa-awards-siemens-elsewedy-300m-contract-to-develop-power-station-1.702637), 2018-02-07: "The turbines are expected to be operational in phases starting from February 29, 2020 and ending on 30 April 2020."

---