GE Power secured a contract from the Shapoorji Pallonji Group to supply power generation equipment for a 220 MW combined cycle power plant in Bhola, Bangladesh. The equipment includes two 6F.03 gas turbines, HRSGs, a steam turbine generator, and controls.

- Type: Contract
- Announced: 2017-09-13
- Where: Bhola, Bangladesh, Bangladesh
- Status: announced
- Capacity: 220 MW
- Products: gas turbines, heat recovery steam generators, steam turbine generator
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [GE Power](https://endata.com/companies/2749.md)
- [SP Group](https://endata.com/companies/23010.md) (customer)
- [Shapoorji Pallonji Group](https://endata.com/companies/26915.md) (customer)

## Sources

- [business-standard.com](https://www.business-standard.com/article/pti-stories/ge-bags-power-equipment-supply-contract-from-spgroup-in-b-desh-117091300982_1.html), 2017-09-13: "Countries in South Asia are accelerating towards achieving energy security which has led to greater investment in the sector."
- [nsenergybusiness.com](https://www.nsenergybusiness.com/contracts/newsge-to-supply-equipment-for-200mw-combined-cycle-power-plant-in-bangladesh-5925477/), 2017-09-14: "The Bhola power project will be an important milestone for the Shapoorji Pallonji Group in Bangladesh, contributing towards increasing the country’s power generation capacity."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.