# Construction begins on $863M Hickory Run Power Station

Tyr Energy, along with partners Kansai Electrical Power Co. and Siemens Group, started construction on the Hickory Run Power Station, a 1,000 MW gas-fueled combined-cycle electrical generation plant in North Beaver Township, Pennsylvania. The plant is expected to be in service by April 2020.

- Type: New facility
- Announced: 2017-08-30
- Where: North Beaver Township, Lawrence County, Pennsylvania, United States
- Value: $863.0M
- Jobs: 500
- Starts operating: Apr 2020
- Status: under construction
- Capacity: 1,000 MW
- Products: electricity
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Tyr Energy](https://endata.com/companies/26647.md)
- [Siemens](https://endata.com/companies/301.md) (partner)
- [ITOCHU](https://endata.com/companies/1234.md) (investor)
- [Kansai Electrical Power Co.](https://endata.com/companies/26648.md) (partner)