# ABB wins order for substation at Cricket Valley Energy Station

ABB won an order from Bechtel Infrastructure and Power to provide a 345 kV gas insulated switchgear substation for the Cricket Valley Energy Station, a new combined cycle gas-fired power plant in Dover, New York.

- Type: Contract
- Announced: 2017-03-16
- Where: Dover, New York, United States
- Status: announced
- Capacity: 1,100 MW
- Products: gas insulated switchgear substation
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md), [Electrical Equipment](https://endata.com/sectors/electrical-equipment.md)

## Companies

- [ABB](https://endata.com/companies/1547.md) (supplier)
- [Bechtel Infrastructure and Power](https://endata.com/companies/22914.md) (customer)

## Sources

- [renewableenergyworld.com](https://www.renewableenergyworld.com/power-grid/grid-modernization/abb-substation-to-enhance-new-york-power-grid/), 2017-03-16: "This advanced GIS substation will boost transmission capacity, improve efficiency and enhance power reliability for millions of New Yorker consumers."

---