# GE supplies steam turbine for PGE Opole power plant

GE has dispatched a steam turbine from its Elbląg factory to the PGE Power Plant in Opole, Poland, as part of the construction of two new power units with a total capacity of 1,800 MWe. The turbine was dispatched on February 9, 2017.

- Type: Contract
- Announced: 2017-02-09
- Where: Opole, Poland
- Status: under construction
- Capacity: 1,800 MWe
- Products: steam turbine, generator, boiler
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [General Electric](https://endata.com/companies/1262.md) (supplier)
- [PGE](https://endata.com/companies/22192.md) (customer)

## Sources

- [gevernova.com](https://www.gevernova.com/news/press-releases/modern-ge-turbine-its-way-elbl%C4%85g-pge-power-plant-opole), 2017-02-14: "The official dispatch of the steam turbine manufactured for the PGE Power Plant in Opole took place on February 9 in the GE Power Turbine Factory in Elbląg."

---