# Techint to complete Norte III power plant project

Techint Engineering & Construction took over the Norte III combined-cycle power plant project in Mexico from Abengoa, renegotiating loans and suppliers to finish the 907 MW plant.

- Type: Contract
- Announced: 2018-08-08
- Where: northern Mexico, Mexico
- Status: under construction
- Capacity: 907 MW
- Products: combined-cycle power plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Abengoa](https://endata.com/companies/4087.md) (partner)
- [Techint Engineering & Construction](https://endata.com/companies/18920.md) (partner)
- [Federal Electricity Commission (CFE)](https://endata.com/companies/18921.md) (customer)