# Masteel awards EPC contract for gas-fired power plant in Ma'anshan, China

Masteel (Ma'anshan Iron & Steel) has awarded an EPC contract for the third-phase gas-fired power plant at its southern plant to a consortium of CISDI Engineering and China MCC20 Group. The contract value is 295,671,277 yuan (approximately $41 million). The plant will include a 1x440 t/h boiler and a 1x145 MW steam turbine.

- Type: Contract
- Announced: 2026-11-05
- Where: Ma'anshan, Anhui, China
- Value: $41.0M (295.7M CNY)
- Status: announced
- Capacity: 1x440 t/h boiler + 1x145 MW steam turbine
- Products: gas-fired power plant, flue gas treatment system
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Ma'anshan Iron & Steel Co., Ltd.](https://endata.com/companies/15260.md) (customer)
- [CISDI Engineering Co., Ltd.](https://endata.com/companies/15261.md) (supplier)
- [China MCC20 Group](https://endata.com/companies/16211.md) (supplier)

## Sources

- [hbzhan.com](https://www.hbzhan.com/news/detail/203024.html), 2026-11-05: "马钢有限南区三期煤气发电主体EPC标段中标结果公告发布。中冶赛迪工程技术股份有限公司、中国二十冶集团有限公司联合体中标，中标金额：295671277元。"

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.