# Doosan Enerbility wins $670M contract for Oman power plant

Doosan Enerbility signed a turnkey EPC contract with a consortium led by Nebras Power to build a 1,700 MW CCGT power plant in Misfah, Oman. The deal is worth approximately 930 billion won ($670 million) and targets completion in April 2029.

- Type: Contract
- Announced: 2026-11-04
- Where: Misfah, about 20 km west of Muscat, Oman
- Value: $670.0M
- Status: announced
- Capacity: 1,700 MW
- Products: steam turbine, generator, combined-cycle gas turbine plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Doosan Enerbility](https://endata.com/companies/9315.md)
- [SEPCOIII](https://endata.com/companies/9767.md) (partner)
- [Nebras Power](https://endata.com/companies/15714.md) (partner)
- [Emirates Utilities Development Company](https://endata.com/companies/15715.md) (partner)
- [Bahwan Infrastructure Services](https://endata.com/companies/15716.md) (partner)

## Sources

- [gulfconstructiononline.com](https://gulfconstructiononline.com/Article/467310/doosan-enerbility-wins-oman-power-plant-deal), 2026-11-04: "Our successful project track record and differentiated strategy in nearby Middle Eastern countries such as Saudi Arabia and Qatar led to this win."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.