# Aker Solutions wins electromechanical contract for 150 MW Tussa II hydropower plant

Aker Solutions was awarded a contract by Tussa Energi to supply all electromechanical equipment for the 150 MW Tussa II hydropower plant in western Norway. Project delivery is scheduled for 2030; the contract value is given only as a range of NOK 500 million to 1.5 billion.

- Type: Contract
- Announced: 2026-06-29
- Where: Tussa hydropower complex, western Norway, Norway
- Status: announced
- Capacity: 150 MW
- Products: Pelton turbines, generators, control systems, transformers, inlet pipes
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Aker Solutions](https://endata.com/companies/1742.md) (supplier)
- [Tussa Energi](https://endata.com/companies/14428.md) (customer)
- [Norconsult](https://endata.com/companies/14429.md) (partner)
- [Aurstad Tunnel](https://endata.com/companies/14430.md) (partner)

## Sources

- [oilprice.com](https://oilprice.com/Company-News/Aker-Solutions-Wins-Hydropower-Contract-for-150-MW-Tussa-II-Plant.html), 2026-06-29: "The contract, valued between NOK 500 million and NOK 1.5 billion under Aker Solutions' classification"

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.