# BEL Valves delivers 55 gate and check valves for ETAP subsea tieback in North Sea

BEL Valves has designed, manufactured and installed 55 high integrity valves on the central processing facility of the ETAP project in the Central North Sea for a subsea tieback to a world-leading energy supplier.

- Type: Contract
- Announced: 2024-11-20
- Where: Eastern Trough Area Project, Central North Sea, United Kingdom
- Status: completed
- Capacity: 50,000 barrels of oil per day field
- Products: gate valves, check valves, hydraulic actuators
- Sectors: [Pumps and Valves](https://endata.com/sectors/pumps-valves.md)

## Companies

- [BEL Valves](https://endata.com/companies/5097.md) (supplier)

## Sources

- [industrialvalvenews.com](https://www.industrialvalvenews.com/featured/bel-valves-secures-large-valve-order-with-world-leading-energy-supplier/), 2024-11-20: "A total of 55 valves have been designed, manufactured and installed onto the central processing facility (CPF) of the Eastern Trough Area Project"

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.