Siemens Energy will supply six F-class gas turbines, six generators and 20-year service agreements for the Misfah and Duqm combined-cycle power plants in Oman, with a combined capacity of nearly 2.6 GW.

- Type: Contract
- Announced: 2026-06-30
- Where: Misfah (Muscat Governorate) and Duqm (Al Wusta Governorate), Oman
- Status: announced
- Capacity: 2.6 GW
- Products: F-class gas turbines, generators, long-term service agreements
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Siemens Energy](https://endata.com/companies/6803.md)
- [Korea Western Power](https://endata.com/companies/2752.md) (partner)
- [Siemens Energy](https://endata.com/companies/6803.md) (supplier)
- [Etihad Water & Electricity](https://endata.com/companies/8353.md) (partner)
- [Doosan Enerbility](https://endata.com/companies/9315.md) (partner)
- [Bahwan Infrastructure Services](https://endata.com/companies/15716.md) (partner)
- [Babcock & Wilcox](https://endata.com/companies/16052.md) (customer)
- [Sepco 3](https://endata.com/companies/51637.md) (partner)
- [Nebras Power Investment Management](https://endata.com/companies/60892.md) (partner)
- [Nama Power and Water Procurement Company](https://endata.com/companies/92765.md) (customer)

## Sources

- [au.marketscreener.com](https://au.marketscreener.com/news/siemens-energy-to-increase-omana-s-energy-production-by-20-percent-ce7f5fdcdd8cf621), 2026-06-30: "The Misfah and Duqm projects reflect Oman's commitment to building a resilient and future-ready energy system."
- [greentechlead.com](https://greentechlead.com/power/siemens-energy-wins-contract-to-supply-2-6-gw-misfah-and-duqm-power-projects-in-oman-54020), 2026-06-30: "Siemens Energy has secured a major contract to supply advanced power generation technology and maintenance services for the Misfah and Duqm Independent Power Producer (IPP) projects in Oman."
- [globalenergyreport.com](https://globalenergyreport.com/article/babcock-wilcox-orders-another-1-gw-of-siemens-energy-turbines-for-ai-data-center/), 2026-08-11: "Ordering the turbines early could let B&W move faster once its next data center power project is ready for construction."
- [bicmagazine.com](https://www.bicmagazine.com/departments/AI-Infrastructure/b-w-secures-1-gw-of-siemens-energy-turbines-for-next-data-ce/), 2026-08-11: "We continue active discussions on other AI data center opportunities and have placed additional orders with Siemens Energy to secure and deliver an additional 1 gigawatt of steam turbines in the next 12 to 15 months to secure speed to markets."
- [energiesmedia.com](https://energiesmedia.com/babcock-wilcox-siemens-energy-turbines/), 2026-08-17: "B&W needed to 'secure speed to market' for upcoming AI data center opportunities."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.