# Doosan Škoda Power wins EUR 125 million turbine modernization order for ORLEN Plock plant

Doosan Škoda Power secured a contract valued at approximately EUR 125 million to modernize two turbine sets (TG4 and TG5) at ORLEN Group's heat and power plant in Plock, Poland. The project includes supply of two 55MW back-pressure turbines and a two-pole generator, with completion planned for 2029.

- Type: Contract
- Announced: 2025-09-03
- Where: Plock, Poland, Poland
- Value: $138.0M (125.0M EUR)
- Status: under construction
- Capacity: 2x55 MW
- Products: back-pressure turbines, generator
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Doosan Škoda Power](https://endata.com/companies/6153.md) (supplier)
- [Orlen](https://endata.com/companies/25981.md) (customer)

## Sources

- [electricaltimes.co.uk](https://www.electricaltimes.co.uk/doosan-skoda-power-successfully-installs-turbine-set-for-orlen-groups-plock-heat-and-power-plant-in-poland/), 2025-09-03: "The newly supplied turbosets and associated technology will have 9% higher efficiency compared to the original technology."

---