# GE Vernova 7HA.03 equipment powers first block of Hsinta power plant in Taiwan

The first block of the Hsinta power plant in Taiwan, powered by GE Vernova's 7HA.03 combined cycle equipment, started delivering 1.3 GW of electricity. This is the first of three blocks for Taiwan Power Company.

- Type: Contract
- Announced: 2025-08-06
- Where: Hsinta, Taiwan, TWN
- Status: completed
- Capacity: 1.3 GW
- Products: 7HA.03 combined cycle equipment
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [GE Vernova](https://endata.com/companies/2947.md)
- [Taiwan Power Company](https://endata.com/companies/6989.md) (customer)

## Sources

- [gasturbineworld.com](https://gasturbineworld.com/ge-vernova-winning-bids/), 2025-08-07: "Powered by GE Vernova’s 7HA.03 combined cycle equipment, the first block of Hsinta power plant started to deliver 1.3 GW of electricity in Taiwan."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.